A busy road on the Essex-Suffolk border is set to close for nearly a month in the build-up to Christmas.
Bures Road, in Dorking Tye, near Sudbury, will be shut 24 hours a day from December 3 to December 20 to allow for work connected to a major National Grid electricity project.
The closure, which will be lifted temporarily on December 13, is part of preparations for the Bramford to Twinstead Reinforcement, which forms part of the Great Grid Upgrade.
A spokesperson for National Grid said: "When the road is closed, there will be no access for vehicles, cyclists or pedestrians.
"We will seek to lift the closure when it is not needed and where it is safe and practical to do so, but please plan accordingly."
The roadworks are expected to cause disruption during the busy pre-Christmas period, with drivers advised to follow a diversion route.
Work will include the construction of a widened site entrance, known as a 'bellmouth,' to allow vehicles safe access to the construction areas.
Balfour Beatty will carry out the works on behalf of National Grid.
The closure will also stop cyclists and pedestrians using the road.
Read more
The signed diversion will take traffic through Assington, along the A134 and through Stoke-by-Nayland towards Nayland before rejoining Bures Road.
National Grid said it will consider reopening the road temporarily if it is safe and practical to do so, but travellers are advised to plan for the full duration of the closure.
Warning signs will go up before the closure and the work area will be clearly marked.
The Bramford to Twinstead Reinforcement is a National Grid project to reinforce the electricity transmission network between Bramford in Suffolk and Twinstead in Essex.
Share